Before application of proof test load, the anchors are to be visually examined, and all defects are to be removed, and if necessary repaired by welding, prior to testing. Proof tests are to be carried out on all anchors after being temporarily assembled. The proof tests are to be in accordance with the values given in Table. The proof load in accordance with Table is to be applied on the fluke at a location one third of the distance from the tip of the fluke to the center of the crown as shown in Figure.
In the case of stockless anchors, both arms are to be tested at the same time, first on one side of the shank, then reversed and tested on the other.
After proof load testing the anchors are to be examined for cracks and other defects, and for excessive deformation due to seating.
Upon completion of the proof load tests, anchors made in more than one piece are to be examined for free rotation of their heads over the complete angle. The anchor shackle that underwent proof load testing is to be fitted to the anchor before shipping to the customer.

Comments

Popular posts from this blog

Introduction to Mooring Line

Anchor Size- rigging table

Introduction to Towline